ZAGREB – LIPOVAC HIGHWAY, SECTION: 2-2 SPAČVA - LIPOVAC, SOUTH, NORTH
MAIN DATA AND AMOUNTS OF EXECUTED WORKS
- Length of the constructed highway: 13 478 m
- Construction of 6 bridges, 5 overpasses and 3 passes: 3 085 m2
- Construction of 4 culverts
- Excavation of humus soil: 158 142 m3
- Adaptation of the formation soil: 174 600 m2
- Replacement of unsuitable soil: 144 817 m3
- Excavation of parallel offlets: 175 345 m3
- Building in of geotextile and geonetwork on embankments : 247 675 m2
- Supply of material and construction of embankments: 688 529 m3
- Bed construction: 355 657 m2
- Sub-base layers 20 & 37cm thick: 236 113 m3
- Sub-base layers stabilized with hydraulic binder (25 cm): 89 110 m3
- Bituminous roadbase: 392 136 m2 (91 888 tons)
- Asphalt-concrete wearing courses: 274 980 m2 (25 276 tons)
- Concrete curbs 18/24 cm: 5 391 m
- Concrete pavement 20 cm thick: 3 609 m2