VIADUCT "DREŽNIK" KARLOVAC - RIJEKA HIGHWAY
- SECTION KARLOVAC - VUKOVA GORICA
- CLIENT:AUTOCESTA RIJEKA-ZAGREB
- MAIN CONTRACTOR:VIADUKT d.d.
- CONTRACT:
- 1-01-02-02-01/1998.
May 8, 1998
01-20/1999.
- CONSTRUCTION PERIOD:
- 2000. - 2001.
- CONSTRUCTION VALUE:
- 8 959 549.13 EUR

- Total length from the dilatation S56 to U74: 632 m
- Width of the viaduct: 2 x 10.5 m
- Surface area of the viaduct: 13.272 m2
- Structure: prestressed AB "I" girders of 180 cm + AB slab of 25 cm
- Spans: 28 and 35 m + 70-meter span over the River Kupa
- Pile-supported bridge.