VIADUCT "MOKRICE" ZAGREB - SPLIT HIGHWAY
- SECTION PIROVAC – SKRADIN
- CLIENT:HRVATSKE AUTOCESTE d.o.o.
- MAIN CONTRACTOR:VIADUKT d.d.
- CONTRACT:
- 45212-400-4365/2004.
June 24, 2004
- CONSTRUCTION PERIOD:
- 2005.
- CONSTRUCTION VALUE:
- 8 927 806 EUR

- Total length: 344.1 m
- Width of the viaduct: 2 x 13.85 m
- Surface area of the viaduct: 9 448.5 m2
- Structure: prestressed AB "I" girders of 200 cm + AB slab of 22 cm
- Viaduct spans - right 38.05 + 6 x 40 + 38.05 m
- Viaduct spans – left 38.05 + 6 x 40 + 38.05 m
- Pier height- right from 15.45 m to 41.43 m
- Pier height – left from 16.90 m too 41.42m