TUNNEL "BRISTOVAC" ZAGREB - SPLIT HIGHWAY

BASIC CHARACTERISTICS OF THE TUNNEL, SECTION: SOUTHERN PORTAL OF THE SV. ROK – MASLENICA TUNNEL
CLIENT:HRVATSKE AUTOCESTE d.o.o.
MAIN CONTRACTOR:VIADUKT d.d.
CONTRACT:
45212-400-5600/2002;
G-28/2002
of March 21, 2002
CONSTRUCTION PERIOD:
2002. - 2003.
CONSTRUCTION VALUE:
9 832 640 EUR


  • Total length of the tunnel tubes: 1372 m
  • Cross-section of the excavation 75 - 85 m2
  • Method of excavation: NATM, drilling + shot firing
  • Excavation category according to RMR classification: III - V
  • Two tunnel tubes, 684 m and 688 m in length
  • Tunnel was cut in a typical karst region, during excavation several larger and smaller caverns were discovered.