TUNNEL "BREZIK" ZAGREB - SPLIT HIGHWAY
- BASIC CHARACTERISTICS OF THE TUNNEL, III C2 ŽUTA LOKVA - LIČKO LEŠĆE
- CLIENT:HRVATSKE CESTE d.o.o.
- MAIN CONTRACTOR:VIADUKT d.d.
- CONTRACT:
- 45212-400-28586/2002.;
G-153/2002 signed on November 20, 2002
- CONSTRUCTION PERIOD:
- 2003. - 2004.
- CONSTRUCTION VALUE:
- 9 050 326 EUR

- Total length of the tunnel tubes: 844 m
- Cross-section of the excavation: 75 - 85 m2
- Excavation method: NATM, drilling + shot firing
- Excavation category according to RMR classification: III - V
- Two tubes: 435 and 409 m long
- Tunnel is located in urban zone, limited excavation zone (of 1 - 2.5 m)
- Construction conditions subject to strict environmental restrictions due the vicinity of a river and drinking water wells.