TUNNEL "VRATA" ZAGREB - RIJEKA HIGHWAY
- BASIC CHARACTERISTICS OF THE TUNNEL (LEFT TUBE), SECTION OŠTROVICA – VRATA
- INVESTOR:ARZ d.d.
- CONTRACTOR:VIADUKT d.d.

- Total length of the tunnel: 257
- Cross-section of the excavation: 75 - 85 m2
- Method of excavation: NATM, drilling + shot firing
- Excavation category according to RMR classification: II - V
- Tunnel was excavated in a dolomite and limestone rock and shale from the Paleozoic on carbonate sediments. Initial length of the tunnel of 325 m was shortened due to the landslide on the western portal in the zone of contact between Paleozoic and carbonate.